executive summary
ES01
Civil Engineering and Development Department (hereafter referred as
¡§CEDD¡¨) is the Project Proponent and the Permit Holder of the Project Cross Bay
Link, Tseung Kwan O (hereinafter referred as ¡§the
Project¡¨) which is a Designated Project to be implemented under Environmental
Permit number EP-459/2013 (hereinafter referred as ¡§the EP-459/2013¡¨ or ¡§the
EP¡¨).
ES02
AUES was awarded the CEDD Contract Agreement No. EDO/04/2018 -
Environmental Team for Cross Bay Link, Tseung Kwan O
(hereinafter called ¡§the Service Contract¡¨). The Services under the Service
Contract is to provide environmental monitoring and audit (EM&A) services
for the Works Contracts pursuant to the requirement of Environmental Team (ET)
under the Approved EM&A Manual to ensure that the environmental performance
of the Works Contracts comply with the requirement specified in the EM&A
Manual and EIA Report of Agreement No. CE 43/2008 (HY) Cross Bay Link, Tseung Kwan O - Investigation and other relevant statutory
requirements.
ES03
To facilitate management, the proposed Works of the project was divided into two Civil Engineering and Development Department (CEDD) Works contracts
included Contract 1 (Contract No. NE/2017/07) and Contract 2 (Contract No. NE/2017/08). The date for
commencement of Contract 1 was 3rd December 2018 while the date
for commencement of Contract 2 was 17th January 2019.
ES04
According to the Approved Environmental Monitoring &
Audit (EM&A) Manual, air quality, noise and water quality
monitoring are required to be
conducted during the construction phase of the Project. As part of the EM&A programme, baseline monitoring shall undertake before the
Project construction work commencement to determine the ambient environment
condition. The baseline air quality, background noise and water quality monitoring
has been carried out
between 21st September 2018 and 13th
November 2018 at the designated and interim locations. The baseline monitoring report under the EP-459/2013 has been compiled
by the ET and verified by Independent Environmental Checker (hereinafter the
¡§IEC¡¦) prior submitted to EPD on 19th November 2018 for
endorsement.
ES05
Since all the Work Contracts under the Project have been completed and it is confirmed
that all construction activities that have the potential to result in a
significant environmental impact were completed, a proposal was prepared and submitted to EPD to
terminate the Construction Phase EM&A program for the Project. The proposal
was approved by EPD on 15th April 2025 and the
construction phase EM&A Programme was terminated on 30th April 2025.
ES06
This
is the Final EM&A Report of Construction Phase for
Contract 1 and 2 (hereinafter ¡¥the Construction Period¡¦), summarizing the
monitoring results and inspection findings during the construction period from 3rd
December 2018 to 30th April 2025.
Environmental Monitoring and Audit Activities in the
Construction Period
ES07
Environmental
monitoring and audit activities under the EM&A program in the Construction
Phase are summarized in the following table.
Table ES-1 Summary Environmental
Monitoring Activities Undertaken in the Construction Period
|
Issues |
Environmental Monitoring Parameters / Inspection |
Sessions |
|
|
Air Quality |
1-Hour TSP |
2265 |
|
|
24-Hour TSP |
657 |
||
|
Construction Noise |
Leq (30min) Daytime |
902 |
|
|
Leq (5min) Evening |
118 |
||
|
Leq (5min) Night |
12 |
||
|
Water Quality |
Marine Water
Sampling |
216 |
|
|
Inspection / Audit |
Contract 1 |
ET Regular
Environmental Site Inspection |
334 |
|
Joint site
audit with Project Consultant and IEC |
76 |
||
|
Contract 2 |
ET Regular
Environmental Site Inspection |
327 |
|
|
Joint site
audit with Project Consultant and IEC |
74 |
||
Breach
of Action and Limit (A/L) Levels
ES08
No air
quality exceedance was recorded throughout the Construction Phase. However, a
total of 38 Action Level and 110 Limit Level exceedances were recorded in
construction noise monitoring. For water quality monitoring, 22 Action Level
and 33 Limit Level exceedances were recorded. The statistics of environmental
exceedance and investigation of exceedance are summarized in the following
table.
Table ES-2 Summary Environmental
Monitoring Parameter Exceedance in the Construction Period
|
Environmental Issues |
Monitoring Parameters |
Exceedances |
||
|
Action Level |
Limit Level |
Total |
||
|
Air
Quality |
1-Hour TSP |
0 |
0 |
0 |
|
24-Hour TSP |
0 |
0 |
0 |
|
|
Construction Noise |
Leq30min Daytime |
31 |
0 |
31 |
|
Leq5min Evening |
1 |
95 |
96 |
|
|
Leq5min Night |
6 |
15 |
21 |
|
|
Water Quality
(Marine Water) |
DO |
3 |
17 |
20 |
|
Turbidity |
0 |
0 |
0 |
|
|
SS |
19 |
16 |
35 |
|
Environmental
Complaint, Notification of Summons and Successful Prosecutions
ES09
Throughout the Construction Period, a total of 55
environmental complaints were lodged under the EM&A Programme
and investigations had performed by ET by auditing the mitigation measures
implemented by the Contractor. After investigation, 16 out of 55 complaints
were considered as project related. The Contractor was strongly advised to
implement and enhance the relevant mitigation measures. Site check was
conducted by ET to check the environmental performance after the situation has
been rectified.
ES10
No environmental summons and prosecutions was received in both contracts
during Construction Period.
ES11
Throughout the Construction Phase, 661 sessions of site inspection
has been carried out by ET to evaluate the site environmental performance of
both Contracts. No non-compliance was recorded. Minor deficiencies were in
general rectified within specific deadlines. The environmental performance of
the Project was therefore considered satisfactory.
ES12
Precision
of the prediction of the EIA on the adverse air quality, noise and water
quality impacts as generated from the construction of the Project is acceptable.
The monitoring performed during the Construction Period is effective for
generating data with the necessary statistical power to categorically identify
or confirm the presence or absence of the predicted environmental impacts
attributable to the works under the Project.
ES13
The
mitigation measures stipulated in Implementation
Schedule for Environmental Mitigation Measures included air quality,
noise and water quality are effective and shall be strictly implemented and
observed throughout the construction period in future of others construction
projects.
Table of Contents
2 Project Organization and Construction
progress and Submission
2.2 Major
Construction Activities
2.3 Summary
of Environmental Submissions
3 Summary of Environmental Monitoring
Programmes and Requirements
3.4 Monitoring
Frequency and Period
3.7 Determination
of Action/Limit (A/L) Levels
3.8 Data
Management and Data QA/QC Control
4.2 Results
Of Air Quality Monitoring
4.3 Conclusion
and Recommendations
5 Construction Noise Monitoring
5.2 Results
of Noise Monitoring
6.2 Results
of water monitoring
6.3 Conclusions
and Recommendations
7.2 Records
of Waste Quantities
7.3 Effectiveness
Of Solid and Liquid Waste Management
8.2 Findings
/ Deficiencies During Construction Period
9.2 Limit
Levels and Event and Action Plan
10 Environmental Complaint and Non-Compliance
10.1 Environmental
Complaint, Summons and Prosecution
11 Implementation Status of Mitigation Measures
11.2 Noise
Mitigation Measure during Operation of the Project
12 Conclusions and Recommendations
List of TABLES
Table 2-1 Documents
Submission under Environmental Permit Requirement
Table 3-1 Summary
of EM&A Requirements
Table 3-2 Designated
Air Quality Monitoring Location recommended in EM&A Manual
Table 3-3 Designated
Construction Noise Monitoring Location recommended in EM&A Manual
Table 3-4 Designated
and interim alternative location for air quality and noise monitoring in the
Construction Period
Table 3-5 Location
of Water Quality Monitoring Station
Table 3-6 Air
Quality Monitoring Equipment
Table 3-7 Construction
Noise Monitoring Equipment
Table 3-8 Water
Monitoring Equipment
Table 3-9 Testing
Method and Reporting Limit of the Chemical Analysis
Table 3-10 Action
and Limit Levels for Air Quality
Table 3-11 Action
and Limit Levels for Construction Noise
Table 3-12 Action
and Limit Levels for Water Quality
Table 4-1 Summary
of 1-hour TSP Monitoring Results
Table 4-2 Summary
of 24-hour TSP Monitoring Results
Table 4-3 Summary
of Breaches of Air Quality A/L Levels
Table 5-1 Summary
of Daytime Construction Noise Impact Monitoring results
Table 5-2 Summary
of Additional Evening time Construction Noise Impact Monitoring results
Table 5-3 Summary
of Additional Night time Construction Noise Impact Monitoring results
Table 5-4 Summary
of Breaches of Construction Noise A/L Levels
Table 6-1 Summary
of Dissolved Oxygen, Turbidity and Suspended Solids of the Water Quality
Monitoring Results at Mid-Ebb Tide in the Construction Period
Table 6-2 Summary
of Dissolved Oxygen, Turbidity and Suspended Solids of the Water Quality
Monitoring Results at Mid-Flood Tide in the Construction Period
Table 6-3 Summary
of Breaches of Water Quality A/L Levels
Table 7-1 Summary
of Quantities of Inert C&D Materials
Table 7-2 Summary
of Quantities of C&D Wastes
Table 8-1 Summary
of Site Inspection
Table 9-1 Actions
in the Event of Landfill Gas Being Detected in Excavations
Table 9-2 Summary
of Landfill Gas Measurement Results
Table 10-1 Statistical
Summary of Environmental Complaints
Table 10-2 Statistical
Summary of Environmental Summons
Table 10-3 Statistical
Summary of Environmental Prosecution
Table 11-1 Environmental
Mitigation Measures in the Reporting Month
Table 11-2
Noise
Mitigation Measure during Operation of the Project
List of
Appendices
Appendix A Project Layout Plan
Appendix B Project Organization Chart &
Contact Details of Key Personnel
Appendix C Monitoring Location (Air
Quality, Noise and Water Quality)
Appendix D Event and Action Plan
Appendix E Graphical plots of Monitoring
Results
Appendix F Waste Flow Table
Appendix G Meteorological Data
Appendix H Implementation Schedule for
Environmental Mitigation Measures (ISEMM)
Appendix I Complaint Log
1.1.1
Civil Engineering and Development Department (hereafter referred
as ¡§CEDD¡¨) is the Project Proponent and the Permit Holder of the Project Cross
Bay Link, Tseung Kwan O (hereinafter referred as ¡§the
Project¡¨) which is a Designated Project to be implemented under Environmental
Permit number EP-459/2013 (hereinafter referred as ¡§the EP-459/2013¡¨ or ¡§the
EP¡¨).
1.1.2
AUES was awarded the CEDD Contract Agreement No. EDO/04/2018 -
Environmental Team for Cross Bay Link, Tseung Kwan O
(hereinafter called ¡§the Service Contract¡¨). The Services under the Service
Contract is to provide environmental monitoring and audit (EM&A) services
for the Works Contracts pursuant to the requirement of Environmental Team (ET)
under the Approved EM&A Manual to ensure that the environmental performance
of the Works Contracts comply with the requirement specified in the EM&A
Manual and EIA Report of Agreement No. CE 43/2008 (HY) Cross Bay Link, Tseung Kwan O - Investigation and other relevant statutory
requirements.
1.1.3
To facilitate management, the proposed Works of Cross
Bay Link, Tseung Kwan O (hereinafter
called ¡§the Project¡¦) was divided into two Civil
Engineering and Development Department (CEDD) Works contracts
included Contract 1 (Contract No. NE/2017/07) and Contract
2 (Contract No. NE/2017/08). The details of each contract Works
are summarized below and the
delineation of each contract is shown in Appendix A.
Contract 1 (Contract No. NE/2017/07)
(i)
400m section of marine viaducts
of steel deck sections including the Eternal Arch Bridge;
(ii)
600m section of marine viaducts
of concrete deck sections;
(iii)
An E&M Plantroom and
associated building services; and
(iv)
E&M provisions.
Contract
2 (Contract No. NE/2017/08)
(i)
Elevated deck structures along Road D9;
(ii)
A 210m section of cycle track and footpath ramp bridge;
(iii)
A 630m section of noise semi-enclosure covering the
entire length of Road D9, and;
(iv)
Lift, staircase,
modification of existing seawall along Road D9, landscaping and miscellaneous
works.
1.1.4
The date for commencement of Contract 1 is 3rd
December 2018 while the date for commencement of Contract 2 is 17th
January 2019.
1.1.5
As part of the EM&A programme,
baseline monitoring shall be undertaken before the Project construction work
commencement to determine the ambient environmental condition. The baseline air quality, background noise
and water quality monitoring has been carried out between 21st September 2018
and 13th November 2018 at the
designated and interim locations. The baseline monitoring report under the EP-459/2013 has been compiled
by the ET and verified by Independent Environmental Checker (hereinafter the
¡§IEC¡¦) prior submitted to EPD on 19th November 2018 for
endorsement.
1.1.6
Since all the
Work Contracts under the Project have been completed and it is confirmed that all construction
activities that have the potential to result in a significant environmental
impact were completed, a proposal was
prepared and submitted to EPD to terminate the Construction Phase EM&A
program for the Project. The proposal was approved by EPD on 15th
April 2025 and the construction phase EM&A Programme was terminated
on 30th
April 2025.
1.1.7
This is the Final EM&A
Report of Construction Phase for Contract 1 and 2 (hereinafter 'the
Construction Period'), summarizing the monitoring results and inspection
findings during the construction period from 3rd December 2018
to 30th
April 2025.
1.2.1
The
Final EM&A Report is structured into the following sections:-
|
Section 1 |
Introduction |
|
Section 2 |
Project Organization and
Construction Progress |
|
Section 3 |
Summary
of Impact Monitoring Requirements |
|
Section 4 |
Air
Quality Monitoring |
|
Section 5 |
Construction
Noise Monitoring |
|
Section 6 |
Water Quality
Monitoring |
|
Section 7 |
Waste
Management |
|
Section 8 |
Site
Inspections |
|
Section 9 |
Landfill Gas Monitoring |
|
Section 10 |
Environmental
Complaints and Non-Compliance |
|
Section 11 |
Implementation
Status of Mitigation Measures |
|
Section 12 |
Conclusions
and Recommendations |
2.1.1
The
project organization is shown in Appendix B. The responsibilities of
respective parties are:
The Project Consultant
2.1.2
The
Project Consultant (hereinafter ¡§the Consultant¡¨) is responsible for overseeing
the construction works and for ensuring that the works are undertaken by the
Contractor in accordance with the specification and contract requirements. The
duties and responsibilities of the Consultant with respect to EM&A are:
¡P
Monitor
the Contractors¡¦ compliance with contract specifications, including the
implementation and operation of the environmental mitigation measures and their
effectiveness
¡P
Monitor
Contractors¡¦, ET¡¦s and IEC¡¦s compliance with the requirements in the Environmental
Permit (EP) and EM&A Manual
¡P
Facilitate
ET¡¦s implementation of the EM&A programme
¡P
Participate
in joint site inspection by the ET and IEC
¡P
Oversee
the implementation of the agreed Event / Action Plan in the event of any
exceedance
¡P
Adhere
to the procedures for carrying out complaint investigation
The Contractor(s) of Works Contract(s)
2.1.3
There
will be one contractor for each individual works contract. The Contractor(s) should report to the Consultant. The duties and responsibilities of the
Contractor are:
¡P
Comply
with the relevant contract conditions and specifications on environmental
protection
¡P
Participate
in the site inspections by the ET and IEC, and undertake any corrective actions
¡P
Provide
information / advice to the ET regarding works programme
and activities which may contribute to the generation of adverse environmental
impacts
¡P
Submit
proposals on mitigation measures in case of exceedances of Action and Limit
levels in accordance with the Event / Action Plans
¡P
Implement
measures to reduce impact where Action and Limit levels are exceeded
¡P
Adhere
to the procedures for carrying out complaint investigation
Environmental
Team (ET)
2.1.4
ET shall
not be in any way an associated body of the Contractor(s) and employed by the Permit Holder
(i.e., CEDD) to conduct the EM&A
programme.
The ET should be managed by the ET Leader. The ET Leader shall be a
person who has at least 7 years¡¦ experience in EM&A and has relevant
professional qualifications. Suitable qualified staff should be included in the
ET, and resources for the implementation of the EM&A programme
should be allocated in time under the Contract(s), to enable fulfillment of the
Project¡¦s EM&A requirements as specified in the EM&A Manual during
construction of the Project. ET
shall report to the Project Proponent and the duties shall include:
¡P
Conduct baseline monitoring,
impact monitoring and post-construction monitoring and the associated in-situ
and laboratory tests to monitor various environmental parameters as required in
the EM&A Manual and the EP
¡P
Analyze
the environmental monitoring and audit data, review the success of EM&A programme and the adequacy of mitigation measures
implemented, confirm the validity of the EIA predictions and identify any
adverse environmental impacts arising
¡P
Carry
out regular site inspection to investigate and audit the Contractors¡¦ site
practice, equipment/plant and work methodologies with respect to pollution
control and environmental mitigation, and effect proactive action to pre-empt
problems
¡P
Monitor
compliance with conditions in the EP, environmental protection, pollution
prevention and control regulations and contract specifications
¡P
Audit
environmental conditions on site
¡P
Report
on the environmental monitoring and audit results to EPD, the Consultant, the IEC and Contractor(s) or their delegated
representatives
¡P
Recommend
suitable mitigation measures to the Contractor in the case of exceedance of
Action and Limit levels in accordance with the Event and Action Plans
¡P
Liaise
with the IEC on all environmental performance matters and timely submit all
relevant EM&A proforma for approval by IEC
¡P
Advise
the Contractor(s) on environmental improvement, awareness, enhancement measures
etc., on site
¡P
Adhere
to the procedures for carrying out complaint investigation
¡P
Set up a dedicated website
where the project information, all environmental monitoring and audit data and
reports described in Condition 5.2 of the EP, and all finalized submissions and
plans required under the EP are to be placed for public inspection
¡P
Upload the environmental
monitoring results to the dedicated website in accordance with requirements of the EP and
EM&A Manual
¡P
To carry out the Operational
Phase Landfill Gas monitoring during effluent drainage system maintenance for
one year
Independent
Environmental Checker (IEC)
2.1.5
IEC
will be employed for this Project.
The Independent Environmental Checker (IEC) should not be in any way an
associated body of the Contractor(s) or the ET for the Project. The IEC should be employed by the Permit Holder
(i.e., CEDD) prior to the
commencement of the construction of the Project. The IEC should have at least 7 years¡¦
experience in EM&A and have relevant professional qualifications. The duty of IEC should be:
¡P
Provide
proactive advice to the Project Consultant and the Project Proponent on
EM&A matters related to the project, independent from the management of
construction works, but empowered to audit the environmental performance of
construction
¡P
Review
and audit all aspects of the EM&A programme
implemented by the ET
¡P
Review
and verify the monitoring data and all submissions in connection with the EP
and EM&A Manual submitted by the ET
¡P
Arrange
and conduct regular, at least monthly site inspections of the works during
construction phase, and ad hoc inspections if significant environmental
problems are identified
¡P
Check
compliance with the agreed Event / Action Plan in the event of any exceedance
¡P
Check
compliance with the procedures for carrying out complaint investigation
¡P
Check
the effectiveness of corrective measures
¡P
Feedback
audit results to ET by signing off relevant EM&A proforma
¡P
Check
that the mitigation measures are effectively implemented
¡P
Report
the works conducted, the findings, recommendation and improvement of the site
inspections, after reviewing ET¡¦s and Contractor¡¦s works, and advices to the
Project Consultant and Project Proponent on a monthly basis.
2.2.1
The commencement of Contract 1 is on 3rd
December 2018. The major construction activities undertaken throughout
the Construction Period included:
Contract
1 (Contract No: NE/2017/07)
Site
Clearance Work at Works Area A
Site Office Setup at Works
Area A
Pre-drilling works at
Portion II
Piling works at Portion II
Concrete Work at Portion V
& Portion II
Structure Steelwork at
Portion V
Metal work at Works Area A
Precast Pier and box girder
installation at Portion II
Stage Concrete for pile caps
at portion II
Welding of steel bracket for
precast shell installation at Portion II
Preparation of precast shell
fabrication at Portion II
Precast shell erection and fabrication
at Portion II
ABWF works, E&M Work and
External Work at Portion V Plant Room Building
Load-out and Transportation
of Steel Main Bridge
Load-out and Transportation
of Floating-in of Steel Bridge Side Span
Fabrication
of bottom deck panels, top deck panels and diaphragm panels at Portion II
Structure works for E&M Building
2.2.2
The commencement of Contract 2 is on 17th
January 2019. The major construction activities undertaken throughout
the Construction Period included:
Contract 2 (Contract No.
NE/2017/08)
Site Clearance Work at Portion III
and VI
Initial Survey at Portion III and VI
UU Detection Work at Portion III and
VI
Fencing Erection Work at Portion II
and VI
Trial Pit and Pre-drill Work at
Portion VI
Bored Pile Work at Portion IV &
VI
Sheet Pile Work at Portion VI
Excavation Work at Portion VI
Wheel Washing Facilities Construction
at Portion VI
RC
construction for U-trough(Portion III)
Seawall
modification
ELS &
manhole construction at SMH012 &SMH011,lift shaft
Noise
barrier installation(Portion VI)
Backfilling
(Portion VI)
Drainage
Installation Work (Portion III)
Footpath and cycle track paving work
2.3.1
The required documents list below shall be to submit to EPD for
retention:
Table 2-1 Documents Submission under Environmental Permit
Requirement
|
EP condition |
Submission to EPD |
Requirement |
Situation |
|
1.11 |
Commencement date of construction of the Project |
no later than 1 month prior to the commencement of
construction of the Project |
Contract 1 notified EPD on 19 Oct 2018 Contract 2 notified
EPD on 12 Dec 2018 |
|
2.3 |
The date of setting up the Community Liaison Group
(CLG), the membership, the terms of reference and the contact details |
At least 1 month before the commencement of
construction of the Project |
CLG
setting has submitted to EPD on 9
Oct 2018 |
|
2.4 |
Management Organization of Main Construction Companies |
No later than 2 weeks before the commencement of
construction of the Project |
Management
Organization of Contract 1 was submitted to EPD on 2 October 2018 Management
Organization of Contract 2 was submitted to EPD on 12 December 2018 |
|
2.5 |
Waste Management Plan (WMP) |
No later than 1 month before commencement of
construction of the Project |
WMP of Contract 1 was
submitted to EPD in 11 October 2018 WMP of Contract 2 was
submitted to EPD in 14 December 2018 |
|
2.6 |
Landscape Mitigation Plan (LSMP) |
No later than 1 month before commencement of
construction of the Project |
LSMP was submitted on 1 Nov 2018 |
|
2.7 |
Detailed Qualitative Landfill Gas Hazards
Assessment (QLGHA) |
No later than 1 month before commencement of
construction of the Project |
QLGHA of the Project was
submitted to EPD on 1 November 2018 |
2.3.2
Upon completed baseline monitoring, a Baseline Monitoring Report was verified by IEC on 19 November
2018 and submitted to EPD on that day for endorsement.
2.3.3
The notification
of Project dedicated website to EPD was made on 9 January 2019 (http://www.envcbltko.hk/).
3.1.1
The Environmental Monitoring and Audit Programmes
and requirements are set out in the Approved EM&A manual. Environmental issues such as air quality,
construction noise and water quality were identified as the key issues during
the construction phase of the Project.
A summary of EM&A programmes and requirements
are
presented in the sub-sections below.
3.2.1
Monitoring parameters of air quality, noise and water quality are
summarized in Table 3-1.
Table 3-1 Summary
of EM&A Requirements
|
Environmental
Issue |
Parameters |
|
Air Quality |
1-hour TSP by Real-Time
Portable Dust Meter; and 24-hour TSP by High Volume
Air Sampler |
|
Noise |
Leq (30min) in six consecutive Leq(5min) between 07:00-19:00 on normal
weekdays Supplementary
information for data auditing, statistical results such as L10 and
L90 shall also be obtained for reference. |
|
Water Quality |
In-situ measurement
¡V Dissolved Oxygen (DO) concentration (mg/L) & saturation (%), pH,
Salinity (mg/L), Temperature (ºC) and Turbidity (NTU); and Laboratory analysis
¡V SS (mg/L) |
Air Quality and Construction Noise
3.3.1
According to
the Approved EM&A Manual Section 5.4
and Section 6.3, three (3) representative air sensitive receivers (ASR)
and four (4) representative noise sensitive receivers
were designated as monitoring stations.
The designated air quality and noise monitoring locations are listed in Table
3-2 and Table 3-3, and illustrated in Appendix C.
Table 3-2 Designated Air
Quality Monitoring Location recommended in
EM&A Manual
|
ID |
Location
in the EM&A Manual |
Currently Situation |
|
AM1 |
Tung Wah
Group of Hospitals Aided Primary School & Secondary School |
Not yet
construct |
|
AM2 |
Lohas Park Stage 2
(Planned Development in Area 86) |
Available for
resident occupation in February 2021 |
|
AM3 |
Lohas Park Stage 3
(Planned Development in Area 86) |
Available for
resident occupation in April 2024 |
Table 3-3 Designated
Construction Noise Monitoring Location recommended by
EM&A Manual
|
ID |
Location |
Currently Situation |
|
CNMS-1 |
Lohas Park Stage
1(Planned Development in Area 86, Package 4) (Southeast facade) |
Available for
resident occupation in November 2019 |
|
CNMS-2 |
Lohas Park Stage 1
(Planned Development in Area 86, Package 6) (Southeast facade) |
Available for
resident occupation in February 2021 |
|
CNMS-3 |
Lohas Park Stage 3
(Planned Development in Area 86, Package 11) (West facade) |
Available for
resident occupation in April
2024 |
|
CNMS-4 |
Tung Wah Group of Hospitals
Aided Primary School & Secondary School (Southwest facade) |
Not yet
construct |
3.3.2
As observed and confirmed by ET and IEC during the joint site visit on 29th August 2018, the
designated air quality and noise
monitoring locations are under construction or yet to construct. It is considered that these
designated locations are not appropriate to perform air quality and noise
monitoring. In this regard, alternative locations were proposed as interim arrangement to
carry out air quality and noise monitoring before occupation of the designated
monitoring location. A letter enclosed with the alternative location proposal
and IEC verification (Our Ref: TCS00975/18/300/L0038) was sent to EPD on 19th
October 2018 and the proposal was agreed by EPD. Therefore, air
quality and construction noise impact monitoring would be performed at the agreed
alternative
locations until the designated sensitive receivers occupied and granted the
premises.
3.3.3
Construction
noise monitoring for Lohas Park Phase 4 was commenced
in November 2019 while 1-Hour TSP air quality and construction noise monitoring
for Lohas Park Phase 6 were commenced in February
2021 regarding the handover of residential units to purchasers. Since power
supply is not available from Lohas Park Phase 6 and
is only available near the site office after Cross Bay Link opened in December
2022, an interim alternative monitoring location AM2b was proposed for the 24-Hour
TSP monitoring of Lohas Park Phase 6 due to the
limitation on the power supply for the HVS.
3.3.4
Upon
the handover of residential units of Lohas Park Phase
10 to purchasers, access permission for 1-Hour & 24-Hour TSP air quality
and construction noise monitoring were requested. 1-Hour TSP air quality and
construction noise monitoring for Lohas Park Phase 10
were commenced on 8 April 2024 upon approved by the Property Management Office
of Lohas Park Phase 10 while installation of HVS for
24-Hour TSP monitoring was rejected by Property Management Office of Lohas Park Phase 10.
3.3.5
The designated and interim alternative monitoring
location for impact air quality and noise
monitoring in the Construction Period are summarized in Table 3-4 and illustrated in Appendix
C.
Table 3-4 Designated and interim alternative location
for air quality and noise monitoring in Construction Period
|
Location ID |
Monitoring
Parameter |
Location |
|
AM2 |
1-Hour TSP Air Quality |
Lohas Park Phase 6 |
|
AM2b |
24-Hour TSP Air Quality |
Near Lohas Park Phase 6 |
|
AM3 |
1-Hour TSP Air Quality |
Lohas Park Phase 10 |
|
AM4 |
1-Hour TSP Air Quality |
Podium of Lohas Park Phase 2A (Le Prestige) |
|
AM5 |
24-Hour TSP Air Quality |
Boundary of Site Office near Junction of Wan Po Road and Wan O Road |
|
CNMS-1 |
Noise (Leq,
L10 & L90) |
Podium of Lohas Park Package 4 |
|
CNMS-2 |
Noise (Leq,
L10 & L90) |
Lohas Park Package 6 |
|
CNMS-3 |
Noise (Leq,
L10 & L90) |
Lohas Park Phase 10 |
|
CNMS-5 |
Noise (Leq,
L10 & L90) |
Podium of Lohas Park Phase 2A (Le Prestige) |
Remark: Since
24-Hour TSP Air Quality monitoring is not granted at AM4 Lohas
Park Phase 2A, the 24-Hour TSP monitoring was therefore proposed at AM5 which
is located at the boundary of the project site office.
Water Quality
3.3.6
According to
Table 7.1 of the
approved EM&A Manual Section 7.4, two Control
Stations (C3 & C4), six (6) sensitive
receivers (CC1, CC2, CC3, CC4, CC13
& SWI1) and one (1) Gradient station (I1) are
recommended to perform water quality monitoring. Details and
coordinate of these water quality monitoring stations are described in Table
3-5 and the locations is shown in Appendix C.
Table 3-5 Location of Water Quality
Monitoring Station
|
Station |
Coordinates |
Description |
|
|
Easting |
Northing |
||
|
CC1 |
843201 |
816416 |
Sensitive
Receiver ¡V
Coral Sites at Chiu Keng Wan |
|
CC2 |
844076 |
817091 |
Sensitive
Receiver ¡V
Coral Sites at Junk Bay |
|
CC3 |
844606 |
817941 |
Sensitive
Receiver ¡V
Coral Sites at Junk Island |
|
CC4 |
845444 |
815595 |
Sensitive
Receiver ¡V
Coral Sites at Fat Tong Chau West |
|
CC13 |
844200 |
817495 |
Sensitive Receiver ¡V Coral Sites at Junk Bay
near Chiu Keng Wan |
|
SWI1 |
845512 |
817442 |
Sensitive
Receiver ¡V Tseung Kwan O Salt Water Intake |
|
C3 |
843821 |
816211 |
Control Station (Ebb Tide) ¡V within Junk Bay |
|
C4 |
844621 |
815770 |
Control Station (Flood Tide) ¡V within Junk Bay |
|
I1 |
844602 |
817675 |
Gradient Station ¡V in between Lam Tin Tunnel (LTT) and CBL |
3.4.1
To according with the approved EM&A Manual, impact monitoring requirements are presented as
follows.
Air Quality Monitoring
3.4.2
Air quality impact monitoring frequency is
as follows:
Once every 6 days of 24-hour TSP and 3 times of 1-hour TSP monitoring; during course of works throughout the construction period
Construction Noise Monitoring
3.4.3
Construction noise monitoring frequency is
as follows:
One set of Leq(30min) measurements in a weekly basis
between 07:00 and 19:00 hours on normal weekdays during course of works as throughout the construction period
If construction works are
extended to include works during the hours of 1900-0700, additional weekly
impact monitoring shall be carried out during evening and night-time works.
Applicable permits under the NCO shall be obtained by the Contractor.
Water Quality (Marine Water) Monitoring
3.4.4
Marine water impact monitoring frequency
is as follows:
Three days
a week, at mid ebb and mid flood tides during course of pile excavation works for the
bridge pier foundations
underway. Moreover, the intervals between 2 consecutive sets of monitoring day
shall not be less than 36 hours.
Air Quality Monitoring
3.5.1
The 24-hour and 1-hour TSP levels shall be measured by following
the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), and Appendix B. If the ET proposes to use a direct
reading dust meter to measure 1-hour TSP levels, it shall submit sufficient
information to the IEC to prove that the instrument is capable
of achieving a comparable results to the HVS. The instrument should be calibrated
regularly, and the 1-hour sampling shall be determined on yearly basis by the
HVS to check the validity and accuracy of the results measured by direct
reading method. The filter paper of 24-hour
TSP measurement shall be determined by HOKLAS accredited laboratory. The equipment used for air quality
monitoring is listed in Table 3-6.
Table 3-6 Air Quality
Monitoring Equipment
|
Equipment |
Model |
|
|
24-hour TSP |
High Volume Air Sampler |
TISCH High
Volume Air Sampler, HVS Model TE-5170 |
|
Calibration Kit |
TISCH Model
TE-5025A |
|
|
1- hour TSP |
Portable Dust Meter |
Sibata LD-5R
Laser Dust Monitor or Sibata LD-3B Laser Dust Monitor |
Noise Monitoring
3.5.2
Sound level meter in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1)
and 804: 1985 (Type 1) specifications shall be used for carrying out the noise
monitoring. The sound level meter
shall be checked using an acoustic calibrator. The wind speed shall be checked with a
portable wind speed meter capable of measuring the wind speed in ms-1. Noise equipment will be used for impact monitoring is
listed in Table 3-7.
Table 3-7 Construction
Noise Monitoring Equipment
|
Equipment |
Model |
|
Integrating Sound Level Meter |
B&K
Type 2238 or Rion NL-31 or Rion
NL-52 or Rion NL-52A |
|
Calibrator |
B&K
Type 4231 or Rion NC-74 or Rion
NC-75 |
|
Portable Wind Speed Indicator |
Anemometer
AZ Instrument 8908 |
Water Quality Monitoring
3.5.3
For
water quality monitoring, the equipment should fulfill the requirement under
the Approved EM&A Manual Section 7.2. The requirement is summarized below:
•
Dissolved Oxygen and Temperature Measuring
Equipment ¡V The instrument should be a portable, weatherproof dissolved oxygen
measuring instrument completed with cable, sensor, comprehensive operation
manuals, and should be operable from a DC power source. It should be capable of
measuring: dissolved oxygen levels in the range of 0-20 mg/L and 0-200%
saturation; and a temperature of 0-45 degrees Celsius. It should have a
membrane electrode with automatic temperature compensation complete with a
cable of not less than 35 m in length. Sufficient stocks of spare electrodes
and cable should be available for replacement where necessary.
•
Turbidity Measurement Equipment ¡V The
instrument shall be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment shall use a DC
power source. It shall have a photoelectric sensor capable of measuring
turbidity between 0-1000 NTU.
•
Salinity Measurement Instrument ¡V A portable salinometer
capable of measuring salinity in the range of 0-40 ppt
should be provided for measuring salinity of the water at each monitoring
location.
•
Water Depth Detector ¡V A portable, battery-operated echo sounder
should be used for the determination of water depth at each designated
monitoring station. A detector affixed to the bottom of the works boat, if the
same vessel is to be used throughout the monitoring programme,
is preferred.
•
Positioning Device ¡V hand-held or boat-fixed type digital Global
Positioning System (GPS) with way point bearing indication or other equipment
instrument of similar accuracy, should be provided and used during water
quality monitoring to ensure the monitoring vessel is at the correct location
before taking measurements.
•
Water Sampling Equipment ¡V A water sampler, consisting of a
transparent PVC or glass cylinder of not less than two liters, which can be
effectively sealed with cups at both ends, should be used. The water sampler
should have a positive latching system to keep it open and prevent premature
closure until released by a messenger when the sampler is at the selected water
depth.
3.5.4
Equipment
used for water quality impact monitoring is listed in Table 3-8.
Table 3-8 Water
Monitoring Equipment
|
Equipment |
Model |
|
A Digital Global Positioning System |
GPS12
Garmin |
|
Water Depth Detector |
Eagle Sonar CUDA 300 |
|
Water Sampler |
A 2-litre transparent PVC
cylinder with latex cups at both ends |
|
Thermometer & DO meter |
YSI
ProDSS Digital Sampling System Water Quality Meter |
|
pH meter |
|
|
Turbidimeter |
|
|
Salinometer |
|
|
Sample Container |
High density polythene
bottles (provided by laboratory) |
|
Storage Container |
¡¥Willow¡¦ 33-litter plastic
cool box with Ice pad |
Air Quality
1-hour TSP
3.6.1
The
1-hour TSP monitor was a brand named ¡§Sibata LD-3 Laser Dust monitor Particle Mass
Profiler & Counter¡¨ which is a
portable, battery-operated laser photometer. The 1-hour TSP meter provides a real
time 1-hour TSP measurement based on 90o light scattering. The 1-hour TSP monitor consists of the
following:
(a.)
A pump
to draw sample aerosol through the optic chamber where TSP is measured;
(b.)
A
sheath air system to isolate the aerosol in the chamber to keep the optics
clean for maximum reliability; and
(c.)
A
built-in data logger compatible with Windows based program to facilitate data
collection, analysis and reporting.
3.6.2
The
equipment used for 24-hour TSP measurement is TISCH,
Model TE-5170 TSP High Volume Air Sampler, which complied with EPA Code of Federal Regulation, Appendix B
to Part 50. The High Volume Air Sampler (HVS) consists of the following:
(a.)
An
anodized aluminum shelter;
(b.)
A
8¡¨x10¡¨ stainless steel filter holder;
(c.)
A
blower motor assembly;
(d.)
A
continuous flow/pressure recorder;
(e.)
A
motor speed-voltage control/elapsed time indicator;
(f.)
A
7-day mechanical timer, and
(g.)
A
power supply of 220v/50 Hz
3.6.3
For HVS for 24-hour TSP monitoring, the HVS is mounted in a
metallic cage with a top for protection and also it is sat on the existing
ground or the roof of building. The
flow rate of the HVS between 0.6m3/min and 1.7m3/min will
be properly set in accordance with the manufacturer¡¦s instruction to within the
range recommended in EPA Code of Federal
Regulation, Appendix B to Part 50. Glass Fiber Filter 8" x 10" of
TE-653 will be used for 24-Hour TSP monitoring and would be supplied by
laboratory. The general procedures
of sampling are described as below:-
A horizontal platform with
appropriate support to secure the samples against gusty wind should be
provided;
No two samplers should be
placed less than 2 meters apart;
The distance between the
sampler and an obstacle, such as building, must be at least twice the height
that the obstacle protrudes above the sample;
A minimum of 2 meters of
separation from any supporting structure, measured horizontally is required;
Before placing any filter media
at the HVS, the power supply will be checked to ensure the sampler work
properly;
The filter paper will be set to
align on the screen of HVS to ensure that the gasket formed an air tight seal
on the outer edges of the filter.
Then filter holder frame will be tightened to the filter hold with swing
bolts. The holding pressure should
be sufficient to avoid air leakage at the edge.
The mechanical timer will be
set for a sampling period of 24 hours (00:00 mid-night to 00:00 mid-night next
day). Information will be recorded
on the field data sheet, which would be included the sampling data, starting
time, the weather condition at current and the filter paper ID with the initial
weight;
After sampling, the filter paper will be collected and transfer
from the filter holder of the HVS to a sealed envelope and sent to a local
HOKLAS accredited laboratory for quantifying.
3.6.4
All the sampled 24-hour TSP filters will be kept in normal air
conditioned room conditions, i.e. 70% HR (Relative Humidity) and 25oC,
for six months prior to disposal.
3.6.5
The HVS used for 24-hour TSP monitoring will be calibrated in two
months interval for in accordance with the manufacturer¡¦s instruction using the
NIST-certified standard calibrator (Tisch Calibration
Kit Model TE-5025A) to establish a relationship between the follow recorder meter
reading in cfm (cubic feet per minute) and the standard flow rate, Qstd, in m3/min. Motor brushes of HVS will be regularly
replaced. The calibration certificates of the air
quality monitoring equipment used for the impact monitoring and the HOKLAS accredited certificate of
laboratory was provided in
Appendix G.
3.6.6
As referred to in the Technical Memorandum (TM) issued under the
NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651:1979 (Type 1)
and 804:1985 (Type 1) specifications shall be used for carrying out the noise
monitoring. Immediately prior to and following each noise measurement the
accuracy of the sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency. Measurements may
be accepted as valid only if the calibration levels from before and after the
noise measurement agree to within 1.0 dB.
3.6.7
All noise measurements will be performed with the meter set to
FAST response and on the A-weighted equivalent continuous sound pressure level (Leq). Leq(30 min) in six
consecutive Leq(5 min) measurements will be used as the
monitoring parameter for the time period between 07:00-19:00 hours on weekdays
throughout the construction period.
3.6.8
The sound level meter will be mounted on a tripod at a height of
1.2 m and placed at the assessment point and oriented such that the microphone
is pointed to the site with the microphone facing perpendicular to the line of sight. The windshield will
be fitted for all measurements. Where a measurement is to be carried out at
a building, the assessment point would normally be at a position 1 m from the
exterior of the building façade. Where a measurement is to be made for noise
being received at a place other than a building, the assessment point would be
at a position 1.2 m above the ground in a free-field situation, i.e. at least
3.5 m away from reflective surfaces such as adjacent buildings or walls.
3.6.9
Immediately prior to and following each noise measurement the
accuracy of the sound level meter will be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements will be accepted as valid
only if the calibration level from before and after the noise measurement
agrees to within 1.0 dB.
3.6.10
Noise measurements will not be made in fog, rain, wind with a
steady speed exceeding 5m/s or wind with gusts exceeding 10m/s. The wind speed will be checked
with a portable wind speed meter capable of measuring the wind speed in m/s.
3.6.11
The sound level meter and calibrator are
calibrated and certified by a laboratory accredited under HOKLAS or any other
international accreditation scheme at yearly basis. The calibration certificates of noise monitoring
equipment used for the impact monitoring was provided in
Appendix G.
Marine
Water Quality
3.6.12
Marine water quality monitoring would be conducted at all designated locations in accordance with Table 7.1 of the approved EM&A Manual. The procedures
of water sampling, in-situ measurement and chemical analysis are described as
below:
A Global
Positioning System (GPS) will be used to ensure that the correct location was
selected prior to sample collection.
A portable, battery-operated echo sounder was used for the determination
of water depth at each designated monitoring station.
The marine water sampler will be lowered into the water body at a
predetermined depth. The trigger system of the sampler is activated with a
messenger and opening ends of the sampler are closed accordingly then the
sample of water is collected.
During the sampling, the
sampling container will be rinsed to
use a portion of the marine water sample before the water sample is transferred
to the container. Upon sampling
completion, the container will be sealed with a screw cap.
Before the sampling process,
general information such as the date and time of sampling, weather condition
and tidal condition as well as the personnel responsible for the monitoring will be recorded on the monitoring field
data sheet.
In-situ measurement including
water temperature, turbidity, dissolved oxygen, salinity, pH
and water depth will be recorded at the identified monitoring station and depth. At
each station, marine water samples will be collected at three depths: 1m below
water surface, 1m above sea bottom and at mid-depth when the water depth
exceeds 6m. Samples at 1m below
water surface and 1m above sea bottom will be collected when the water depth is
between 3m and 6m. And sample at
mid-depth will be taken when the water depth is below 3m.
For the in-situ measurement, two consecutive
measurements of sampling depth, temperature, dissolved oxygen, salinity,
turbidity and pH concentration will be measured at the sea. The YSI ProDSS Multifunctional Meter will be retrieved
out of the water after the first measurement and then re-deployed for the
second measurement. Where the
difference in the value between the first and second readings of each set is
more than 25% of the value of the first reading, the reading is discarded and
further readings is taken.
Marine
water sample will be collected by using a water sampler. The high-density
polythene bottles will be filled after the water sample collected from the
sea. Before the water sample being
fills into the sampling bottles, the sampling bottles will be pre-rinsed with
the same water sample. The sampling
bottles will then be packed in cool-boxes (cooled at 4OC without
being frozen), and delivered to HOKLAS accredited laboratory for the
chemical analysis as followed APHA Standard
Methods for the Examination of Water and Wastewater 19ed 2540D, unless otherwise specified.
3.6.13
Before each round of monitoring, the
dissolved oxygen probe will be calibrated by wet bulb method; a zero check in
distilled water will be performed with the turbidity and salinity probes. The
turbidity probe also will be checked with a standard solution of known NTU and
known value of the pH standard solution were used to check the accuracy of pH value before each monitoring day. Moreover, all in-situ measurement equipment used marine water
monitoring will be calibrated at three months interval.
Laboratory Analysis
3.6.14
All water samples included the duplicate samples, was tested with
chemical analysis as specified in the EM&A Manual by a
HOKALS accredited laboratory - ALS Technichem (HK) Pty Ltd. The
chemicals analysis method and reporting limit show Table 3-9.
Table 3-9 Testing
Method and Reporting Limit of the Chemical Analysis
|
Parameter |
ALS Method Code |
In-house
Method Reference (1) |
Reporting Limit |
|
Total Suspended Solids |
EA025 |
APHA 2540D |
1 mg/L |
Note:
1.
The exact method
shall depend on the laboratory accredited method. APHA
= Standard Methods for the Examination of Water and Wastewater by the American
Public Health Association.
3.6.15
The determination works will start within 24 hours after collection
of the water samples or within the holding time as advised by the laboratory.
Meteorological Information
3.6.16
The meteorological information including wind direction, wind speed,
humidity and temperature etc. of impact monitoring is extracted from
the closest Tseung Kwan
O Hong Kong
Observatory Station. Moreover, the data of rainfall and air pressure would be
extracted from King¡¦s Park Station.
3.6.17
For
marine water quality monitoring, tidal information would be referred to tide
gauge at Tai Miu Wan.
3.7.1
The baseline results form the basis for determining the
environmental acceptance criteria for the impact monitoring. A summary of the Action/Limit (A/L)
Levels for air quality, construction noise and water quality are shown in Tables
3-10, 3-11 and 3-12 respectively.
Table
3-10 Action & Limit Levels of Air
Quality (1-Hour & 24-Hr TSP)
|
Monitoring Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
|
1-Hour TSP |
24-Hr TSP |
1-Hour TSP |
24-Hr TSP |
|
|
AM2 |
278 |
NA |
500 |
NA |
|
AM2b |
NA |
190 |
NA |
260 |
|
AM3 |
278 |
NA |
500 |
NA |
|
AM4 |
278 |
NA |
500 |
NA |
|
AM5 |
NA |
190 |
NA |
260 |
|
Note: 1-Hour
& 24-Hr TSP of Action Level = (Average
Baseline Results ¡Ñ 1.3 + Limit
level)/2 |
||||
Table 3-11 Action and Limit Levels for
Construction Noise, dB (A)
|
Monitoring Location |
Action Level |
Limit Level |
|
CNMS-1 CNMS-2 CNMS-3 CNMS-5 |
Time Period: 0700-1900 hours on normal weekdays (Leq30min) |
|
|
When
one or more documented complaints are received |
75 dB(A) |
|
|
Time Period: 1900-2300 hours on all days (Leq15min) |
||
|
When
one or more documented complaints are received |
55 dB(A) |
|
|
Remarks: 1.
Construction noise monitoring
will be resumed at the designated locations CNMS-2, CNMS-3 and CNMS4 once
they are available and permission are granted; 2.
The designated locations
CNMS-2 and CNMS-3 are located at residential building which are still under construction, Limit
Level of 75dB(A) will be adopted until they are occupied; 3.
The designated location
CNMS-4 is located at
planned school and still not yet to construction. When the school occupied and operated, Limit Level of 70dB(A) should be
adopted and should be reduced to 65dB(A) during examination period; and 4.
If
construction works are required during restricted hours, the conditions
stipulated in the construction noise permit issued by the
Noise Control Authority shall be followed. |
||
Table
3-12 Action and Limit
Levels for Water Quality
|
Monitoring Station |
Depth Average of SS (mg/L) |
|||||
|
Action Level |
Limit Level |
|||||
|
CC1 |
7.8 |
OR
120% of upstream control station at the same tide of the same day (Control Station C3 at Ebb tide and Control Station C4 at Flood tide),
whichever is higher |
9.3 |
OR
130% of upstream control station at the same tide of the same day (Control Station C3 at Ebb tide and Control Station C4 at Flood tide)
, whichever is higher |
||
|
CC2 |
9.0 |
9.2 |
||||
|
CC3 |
8.2 |
9.0 |
||||
|
CC4 |
13.8 |
15.4 |
||||
|
CC13 |
8.9 |
10.3 |
||||
|
SWI1 |
8 mg/L |
10 mg/L |
||||
|
|
||||||
Monitoring Location |
Dissolved
Oxygen (mg/L) |
|||||
|
Depth
Average of Surface and Mid-depth |
Bottom |
|||||
|
Action
Level |
Limit Level |
Action
Level |
Limit Level |
|||
|
CC1 |
5.8 |
5.7 |
5.3 |
5.2 |
||
|
CC2 |
5.8 |
5.7 |
5.3 |
5.1 |
||
|
CC3 |
5.5 |
5.4 |
4.9 |
4.7 |
||
|
CC4 |
5.7 |
5.7 |
5.5 |
5.4 |
||
|
CC13 |
5.6 |
5.5 |
5.3 |
5.2 |
||
|
SWI1 |
5.4 |
4.8 |
5.1 |
5.0 |
||
|
|
||||||
|
Monitoring Location |
Depth Average of Turbidity (NTU) |
|||||
|
Action Level |
Limit Level |
|||||
|
CC1 |
5.8 |
OR
120% of upstream control station at the same tide of the same day (Control Station C3 at Ebb tide and Control Station C4 at Flood tide)
, whichever is higher |
6.0 |
OR
130% of upstream control station at the same tide of the same day (Control Station C3 at Ebb tide and Control Station C4 at Flood tide)
, whichever is higher |
||
|
CC2 |
4.6 |
5.5 |
||||
|
CC3 |
4.8 |
5.4 |
||||
|
CC4 |
6.1 |
7.1 |
||||
|
CC13 |
6.0 |
6.3 |
||||
|
SWI1 |
6.1 |
7.1 |
||||
3.7.2
Should
non-compliance of the environmental quality criteria occurs, remedial actions
will be triggered according to the Event and Action Plan which presented in Appendix
D.
3.8.1
All monitoring data will be handled by the ET¡¦s in-house data recording and
management system. The monitoring data recorded in
the equipment will be downloaded directly from the equipment at the end of each
monitoring day. The downloaded
monitoring data will input into a computerized database properly maintained by
the ET. The laboratory results will
be input directly into the computerized database and checked by personnel other
than those who input the data.
3.8.2
For monitoring parameters that require laboratory analysis, the
local laboratory shall follow the QA/QC requirements as set out under the
HOKLAS scheme for the relevant laboratory tests.
4.1.1
Total Suspended Particulate (TSP) levels monitoring and audit
should be performed by the ET to ensure any deteriorating air quality could be
readily detected and timely actions taken to rectify the situation. 1-hour TSP
or 24-hour TSP should be measured to show the impacts of construction dust on
air quality.
4.2.1
Throughout the Construction Period, a total of 2265 sessions
of 1-hour TSP and 657 sessions of 24-hour TSP air quality monitoring were carried
out at designated monitoring locations. The monitoring results
are summarized in Tables 4-1 to 4-2, and the relevant graphical
plots are shown in Appendix E. Breaches
of air quality A/L levels and statistical analysis of compliance for air
quality monitoring results are summarized in Table 4-3. Meteorological data during the Construction Period are shown in Appendix G.
Table 4-1 Summary
of 1-hour TSP Monitoring results
|
Monitoring
Location |
ASR
ID in EIA |
Predicted
Maximum Mitigated 1-hour TSP Concentration in EIA (£gg/m3) |
1-hour
TSP Concentration (£gg/m3) Average (range) |
Monitoring Period |
Number of Sessions |
|
AM2 |
A13 |
475 |
69 (19
¡V 137) |
4
Feb 2021 to 28 Apr 2025 |
819 |
|
AM3 |
A16 |
412 |
51
(10
¡V 126) |
8
Apr 2024 to 28 Apr 2025 |
204 |
|
AM4 |
A1 |
255 |
69
(18
¡V 124) |
4
Dec 2018 to 28 Apr 2025 |
1242 |
Table 4-2 Summary of
24-hour TSP Monitoring results
|
Monitoring
Location |
ASR
ID in EIA |
Predicted
Maximum Mitigated 24-hour TSP Concentration in EIA (£gg/m3) |
24-hour
TSP Concentration (£gg/m3) Average (range) |
Monitoring Period |
Number of Sessions |
|
AM2(1)
|
A13 |
124 |
69
(13
¡V 186) |
13
Jul 2021 to 29 Apr 2025 |
243 |
|
AM5(2) |
A1 |
98 |
91 (13
¡V 188) |
3
Dec 2018 to 29 Apr 2025 |
414 |
(1)AM2
includes the data of both alternative location AM2a and relocated AM2b
(2)Since
there is no ASR in EIA for the alternative location AM5, the predicted maximum
mitigated 24-hour TSP concentration of ASR A1 which is the closest ASR is
referenced for comparison.
Table 4-3 Summary of
Breaches of Air Quality A/L Levels
|
Monitoring Parameters |
Action Level |
Limit Level |
Status |
|
1-hour TSP |
0 |
0 |
No NOE
of Air quality exceedance was issued |
|
24-hour TSP |
0 |
0 |
Conclusions
4.3.1
According to the EIA, with implementation of the
recommended mitigation measures as well as the relevant control requirements as
stipulated in the Air Pollution Control (Construction Dust) Regulation, no
adverse residual impacts are predicted at all the ASRs during the construction
phase.
4.3.2
The weather throughout the Construction Period was
typical Hong Kong climate including rainy season (Apr to Oct) and dry season
(Nov to Mar next year). The major dust sources in the Construction Period are
construction activities by the Project, as well as traffic emission from Wan Po Road and Wan O Road.
4.3.3
According to the monitoring results, it
was concluded that all the 1-hour TSP and 24-hour
TSP monitoring results at the designated monitoring
location throughout the Construction
Period were below the Action/Limit Levels. No
exceedances were recorded during the monitoring. Neither NOE nor the associated
remedial actions were required for air quality during the Construction Period. Under
the construction dust suppression measures as provided by the Contractor, the
impact monitoring results were generally fulfilled of the environmental quality
criteria of the parameter and comparable to EIA.
4.3.4
The
predicted TSP concentration level with provided mitigation measures during the
construction phase at the designated monitoring locations based on Section
5.5.6 and Table 5.9 of the EIA report are shown in Table 4-1 and 4-2 respectively.
Based on the monitoring results, it is shown that the average 1-hour and 24-hour
TSP concentrations recorded at the monitoring locations are below the predicted
TSP concentration in EIA. Other factor such as adverse weather conditions and influence
of continental airstream with severe air pollution would affect the measured
TSP concentration and cause high fluctuation during the Construction Period.
4.3.5
The air
quality monitoring performed during the Construction Period are effective for
generating data with the necessary statistical power to categorically identify
or confirm the presence or absence of the predicted environmental impacts
attributable to the works under the Project. The construction dust suppression
measures as recommended in the Implementation Schedule for
Environmental Mitigation Measures (ISEMM) is also proven effective and
adequate.
Recommendations
4.3.6
The air quality mitigation measures stipulated in ISEMM should be strictly observed throughout the
construction period in future of others construction
projects.
5.1.1
The construction noise level in terms of A-weighed equivalent
continuous sound pressure level (Leq) measured at all
designated monitoring locations should be carried out to ensure that any
deteriorating construction noise could be readily detected and timely action
taken to rectify the situation throughout the Construction Period.
5.2.1
Throughout
the Construction Period, a total of 902
sessions of daytime noise monitoring were conducted at designated monitoring locations:
CNMS-1, CNMS-2, CNMS-3, and interim alternative monitoring location CNMS-5
respectively. During the Construction Period, noise monitoring were not performed
under fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts
exceeding 10 m/s of weather condition.
5.2.2
A total of 118 additional evening time noise monitoring and 12 additional night time noise
monitoring were also performed at monitoring locations CNMS-1,
CNMS-2, and CNMS-5 during
the Construction Period. The noise monitoring results throughout the
Construction Period are summarized in Table 5-1 to Table 5-3, and
the relevant graphical plots are shown in
Appendix E
Table 5-1 Summary
of Daytime Construction Noise Monitoring Results
|
Monitoring Location |
NSR ID in EIA |
Predicted
Mitigated Noise Level dB(A) in EIA |
Leq, 30min (dB(A)) (Range) |
Monitoring Period |
Number of Sessions |
|
CNMS-1 |
R12 |
73 |
51.7
¡V 74.2 |
8
Nov 2019 to 28 Apr 2025 |
288 |
|
CNMS-2 |
R14 |
74 |
49.2 ¡V 74.6 |
4 Feb 2021 to 28 Apr 2025 |
222 |
|
CNMS-3 |
R27 |
73 |
53.2 ¡V 67.7 |
8 Apr 2024 to 28 Apr 2025 |
56 |
|
CNMS-5 |
R2 |
63 |
54.3 ¡V 72.6 |
4 Dec 2018 to 28 Apr 2025 |
336 |
Table 5-2 Summary
of Additional Evening Time Construction Noise Monitoring Results
|
Monitoring Location |
Leq, 5min (dB(A)) (Range) |
Monitoring Period |
Number of Sessions |
|
CNMS-1 |
49.7
¡V 61.2 |
14
Nov 2019 to 30 Dec 2021 |
41 |
|
CNMS-2 |
44.6
¡V 52.5 |
18 Jun 2021 to 30 Dec 2021 |
4 |
|
CNMS-5 |
58.5 ¡V 64.0 |
15 Mar 2019 to 30 Dec 2021 |
73 |
Table 5-3 Summary
of Additional Night Time Construction Noise Monitoring Results
|
Monitoring Location |
Leq, 5min (dB(A)) (Range) |
Monitoring Period |
Number of Sessions |
|
CNMS-1 |
49.6
¡V 54.3 |
18
Jun 2021 to 14 Dec 2021 |
4 |
|
CNMS-2 |
47.9 ¡V 51.4 |
18
Jun 2021 to 14 Dec 2021 |
4 |
|
CNMS-5 |
55.9 ¡V 57.1 |
18
Jun 2021 to 14 Dec 2021 |
4 |
5.2.3
Throughout the Construction Period, a
total of 38 noise complaints were received (which trigger an Action Level), and 110 Limit Level exceedance were recorded. NOEs were
issued to relevant parties upon confirmation of the monitoring result.
Investigation had been conducted by ET and the investigation results were shown
in corresponding Monthly EM&A Reports. Breaches of construction noise A/L
levels and statistical analysis of compliance for construction noise monitoring
results are summarized in Table 5-4.
Table 5-4
Summary of Breaches of Construction Noise A/L Levels
|
Monitoring Parameters |
Action Level |
Limit Level |
Project related exceedance |
Status |
|
Leq (30min)
Daytime |
31 |
0 |
15 |
Investigation for all the exceedances and
noise complaints and had been conducted according to the Event and Action
Plan in the EM&A Manual and presented in the relevant monthly EM&A
reports. All the environmental complaint received during construction phase
has been resolved. |
|
Leq (5min) Evening
Time |
1 |
95 |
0 |
|
|
Leq (5min) Night
Time |
6 |
15 |
0 |
5.2.4
According to the EIA, the noise impact
associated with unmitigated construction activities for the proposed Project
works would cause exceedance of the daytime construction noise criterion at the
nearby NSRs during the normal working hours. Therefore, good site practices and
mitigation measures including the use of quiet plant and working methods and
erection of movable noise barriers to alleviate the noise impact. With the good
site practices and mitigation measures in place, no residual impacts are
predicted at all the NSRs.
5.2.5
According
to the EIA report Section 6.6.5 and Table 6.9, the predicted construction noise
level with provided mitigation measures during the construction phase at four
residential monitoring locations are 67 dB(A), 74 dB(A), 73 dB(A), and 63 dB(A)
respectively. In comparison with the
EIA prediction of construction noise level, the range of the measured impact
noise levels throughout the construction phase at monitoring stations CNMS-1,
CNMS-2, and CNMS-3 were below the predicted level. However, results showed that
CNMS-5 has a higher range of measured noise levels (54.3 ¡V 72.6 dB (A)) compared
to the predicted level, which might be
due to external noise sources such as traffic noises during the monitoring
sessions.
5.2.6
In accordance with the investigation
results, 15 out of 38 Action Level exceedances were considered project-related.
Upon receipt of the complaint, the Contractor took immediate action to
implement appropriate noise mitigation measures to further reducing the noise
impact. A joint site inspection was also carried out to verify the
implementation of the associated mitigation measures, and these were considered
effective. With regard to the evening and night-time action level exceedances,
the investigation results demonstrated that these were not related to the
project. Nevertheless, the Contractor was reminded to strictly implement the
noise mitigation measures as far as practicable to reduce to noise impact to
the public.
5.2.7
Regarding the Limit Level exceedances of
the monitoring, no Limit Level exceedance was recorded in daytime construction
noise monitoring. However, a total of 110 Limit Level exceedances were recorded
and evening and night-time construction noise monitoring. According to the
investigation results, the exceedances recorded were considered as project
unrelated. Based on the graphical plot of the monitoring result, there are
trends of narrow down of monitoring exceedances due to construction activities
and the return of ambient environmental conditions in comparison with the
baseline data.
5.2.8
It is considered that the construction
noise monitoring performed during the Construction Period are effective for
generating data with the necessary statistical power to categorically identify
or confirm the presence or absence of the predicted environmental impacts
attributable to the works under the Project.
5.2.9
Leq(30min) monitoring results registered
consistent compliance of the parameter with environmental quality criteria
throughout the Construction Period, indicating that the prediction of EIA
prediction on the adverse noise nuisance to be generated from the construction
of the Project is in general acceptable and the recommended environmental
mitigation measures as stipulated in ISEMM are also
adequate.
Recommendations
5.2.10
The construction noise mitigation measures
stipulated in ISEMM shall be
strictly observed throughout the construction period
in future of others construction
projects.
6.1.1
The EIA Report has assessed the water quality impacts associated
with the Project. According to the EIA Report, the water quality impact could
be minimized with the implementation of mitigation measures. The water quality
monitoring shall be necessary to undertake during the construction phase.
Moreover, regular site inspections and audits undertaken to ensure that
runoff/wastewater control and the recommended mitigation measures were properly
implemented.
6.1.2
According to the approved EM&A Manual Section 7.6.1, the impact
marine water quality monitoring work shall be carried out during the CBL piling
and pile excavation works (marine construction activity) of the Project. Impact
marine water quality monitoring was commenced in December 2018 when CBL piling
and pile excavation works started.
6.2.1
According to Table 7.1 of the
approved EM&A Manual Section 7.4, two Control Stations (C3 &
C4), six (6) sensitive receivers (CC1, CC2, CC3, CC4, CC13 & SWI1)
and one (1) Gradient station (I1) are recommended to
perform water quality monitoring.
6.2.2
A total of 216 sampling days
were performed for marine water monitoring at nine designated locations.
Monitoring results of 3 key parameters: Dissolved oxygen (DO), turbidity, and
suspended solids are summarized in Tables 6-1 to 6-2:
|
ID |
Dissolved Oxygen average
(mg/L) (range) |
Turbidity (NTU) average (range) |
Suspended solid (mg/L)
average (range) |
Monitoring Period |
|
|
Surface
& Mid Layer |
Bottom Layer |
||||
|
CC1 |
7.04 (5.07 ¡V 10.18) |
6.72 (4.44
¡V9.26) |
1.37 (0.06 ¡V 3.86) |
3.50 (1.00 ¡V 10.43) |
3 Dec 2018 to 29 Apr 2020 |
|
CC2 |
6.99 (5.18 ¡V 9.40) |
6.6 (4.47 ¡V
8.73) |
1.63 (0.32 ¡V 4.40) |
3.58 (1.00 ¡V 9.10) |
3 Dec 2018 to 29 Apr 2020 |
|
CC3 |
6.97 (5.37 ¡V 11.34) |
6.47 (4.57 ¡V
8.36) |
1.73 (0.41 ¡V 4.42) |
3.66 (1.00 ¡V 12.07) |
3 Dec 2018 to 29 Apr 2020 |
|
CC4 |
6.94 (5.29 ¡V 9.61) |
NA |
1.53 (0.17 ¡V 4.69) |
3.89 (1.00 ¡V 18.05) |
3 Dec 2018 to 29 Apr 2020 |
|
CC13 |
7 (5.21 ¡V 9.94) |
6.69 (4.47 ¡V
9.33) |
1.39 (0.15 ¡V 4.18) |
3.71 (1.00 ¡V 12.25) |
3 Dec 2018 to 29 Apr 2020 |
|
SWI1 |
6.99 (5.37 ¡V 10.44) |
6.86 (4.86 ¡V 9.53) |
1.40 (0.16 ¡V 4.79) |
3.86 (1.00 ¡V 15.43) |
3 Dec 2018 to 29 Apr 2020 |
|
C3 |
6.88 (4.62 ¡V 9.13) |
6.59 (4.34 ¡V 8.64) |
1.68 (0.11 ¡V 4.05) |
3.78 (1.00 ¡V 10.92) |
3 Dec 2018 to 29 Apr 2020 |
|
C4 |
6.89 (4.77 ¡V 9.00) |
6.63 (4.33 ¡V 8.83) |
1.61 (0.20 ¡V 5.07) |
3.55 (1.00 ¡V 11.03) |
3 Dec 2018 to 29 Apr 2020 |
Remark:
No Dissolved Oxygen (Bottom) monitoring data available for CC4 due to the water
depth measured at CC4 during the monitoring days were less than 3 meters.
|
Station ID |
Dissolved Oxygen average
(mg/L) (range) |
Turbidity (NTU) average (range) |
Suspended solid (mg/L)
average (range) |
Monitoring Period |
|
|
Surface &
Mid Layer |
Bottom Layer |
||||
|
CC1 |
7.04 (5.42 ¡V 9.47) |
6.71 (4.76 ¡V 9.36) |
1.42 (0.07 ¡V 4.00) |
3.59 (1.00 ¡V 10.55) |
3 Dec 2018 to 29 Apr
2020 |
|
CC2 |
6.98 (5.13 ¡V 9.26) |
6.60 (4.49 ¡V 8.58) |
1.61 (0.26 ¡V 4.59) |
3.64 (1.00 ¡V 11.88) |
3 Dec 2018 to 29 Apr
2020 |
|
CC3 |
6.95 (5.35 ¡V 9.61) |
6.45 (4.64 ¡V 9.03) |
1.72 (0.31 ¡V 4.30) |
3.54 (1.00 ¡V 13.77) |
3 Dec 2018 to 29 Apr
2020 |
|
CC4 |
6.95 (5.30 ¡V 9.59) |
NA |
1.59 (0.04 ¡V 6.06) |
3.88 (1.00 ¡V 14.15) |
3 Dec 2018 to 29 Apr
2020 |
|
CC13 |
7.00 (5.49 ¡V 10.31) |
6.69 (4.81 ¡V 9.11) |
1.47 (0.36 ¡V 5.25) |
3.89 (1.00 ¡V 15.42) |
3 Dec 2018 to 29 Apr
2020 |
|
SWI1 |
7.04 (5.44 ¡V10.60) |
6.85 (4.84 ¡V 10.10) |
1.40 (0.14 ¡V 5.20) |
3.85 (1.00 ¡V 14.58) |
3 Dec 2018 to 29 Apr
2020 |
|
C3 |
6.91 (5.01 ¡V 9.59) |
6.59 (4.43 ¡V 8.57) |
1.66 (0.25 ¡V 5.73) |
3.61 (1.00 ¡V 10.42) |
3 Dec 2018 to 29 Apr
2020 |
|
C4 |
6.92 (5.18 ¡V 9.42) |
6.63 (4.30 ¡V 8.75) |
1.65 (0.35 ¡V 3.80) |
3.63 (1.00 ¡V 10.60) |
3 Dec 2018 to 29 Apr
2020 |
Remark:
No Dissolved Oxygen (Bottom) monitoring data available for CC4 due to the water
depth measured at CC4 during the monitoring days were less than 3 meters.
6.2.3
Throughout the Construction Period, a total of 22 Action
Level and 33 Limit Level exceedances were recorded. NOEs were issued to
relevant parties upon confirmation of the monitoring result. Investigation had
been conducted by ET and the investigation result shown in corresponding
Monthly EM&A Reports. Breaches of water quality A/L levels and statistical
analysis of compliance for water quality results are summarized in Table
6-3.
Table 6-3 Summary
of Breaches of Water Quality A/L Levels
|
Monitoring Parameters |
Action Level |
Limit Level |
Project related exceedance |
Status |
|
DO |
3 |
17 |
0 |
Investigation
for all the exceedances had been conducted according to the Event and Action
Plan in the EM&A Manual and presented in the relevant monthly EM&A
reports. |
|
Turbidity |
0 |
0 |
0 |
|
|
SS |
19 |
16 |
0 |
6.2.4
Investigation
for all the exceedances had been conducted in accordance with the Event and
Action Plan in the EM&A Manual. According to the investigation findings,
the exceedances were concluded as project unrelated as the water quality
mitigation measures were properly implemented without any abnormal and turbid
discharge. Other factors such as seasonal changes, rainfall and tidal
conditions may contribute to the exceedances resulted in the monitoring. Both
the findings and the conclusion has presented in the relevant monthly EM&A report.
Although the exceedances recorded are concluded as project unrelated, both
Contractors are reminded to pay special attention on water quality mitigation
measures and should fully implement the measures recommended in the EM&A
Manual, in particular to prevent
construction site runoff and other pollutants from flowing to local sewage
system and coral sites. .
6.2.5
All
the environmental complaint due to water quality issues as received during construction
phase has resolved.
Conclusions
6.3.1
The graphical plot of DO, Turbidity and SS monitoring result shown
that ambient environmental conditions in comparison with baseline data has been
slowly resume due to construction activities narrow down.
6.3.2
Throughout the construction period, water quality monitoring
recorded that most parameters consistently met environmental quality standards.
This indicates that the projection of the impact of the EIA on the construction
of the project is acceptable. Also, the recommended environmental mitigation
measures prescribed by the ISEMM are also adequate.
Recommendations
6.3.3
The water quality mitigation measures stipulated in ISEMM shall be strictly observed throughout the construction period in future of others construction projects which near with watercourse
7.1.1
Waste management would be carried out by an on-site Environmental
Officer or an Environmental Supervisor from time to time.
7.2.1
All
types of waste arising from the construction work are classified into the
following:
l Construction & Demolition (C&D)
Material;
l Chemical Waste; and
l General Refuse
7.2.2
The quantities of waste for disposal in the
Construction Period by mean of Waste Flow Table are presented in Appendix
F. The Contractor was
reminded that, whenever possible, materials were reused on-site as far as
practicable. Summary of total waste
generated from construction phase of the Project is shown in Table
7-1 and Table 7-2.
Table 7-1 Summary of Quantities
of Inert C&D Materials
|
Type of Waste |
Quantity |
Total (¡¥000 m3) |
Disposal Location |
|
|
Contract
1 |
Contract
2 |
|||
|
C&D Materials (Inert) (¡¥000
m3) |
17.886 |
69.964 |
87.85 |
- |
|
Reused in this Contract
(Inert) (¡¥000m3) |
0 |
0.358 |
0.358 |
- |
|
Reused in other Projects
(Inert) (¡¥000m3) |
0 |
0 |
0 |
- |
|
Disposal as Public Fill
(Inert) (¡¥000m3) |
18.162 |
68.707 |
86.869 |
TKO-137 |
|
Imported Fill (Inert) (¡¥000 m3) |
0.626 |
13.111 |
13.737 |
- |
Table 7-2 Summary
of Quantities of C&D Wastes
|
Type of Waste |
Quantity |
Total |
Disposal Location |
|
|
Contract
1 |
Contract
2 |
|||
|
Recycled Metal (¡¥000 kg) |
0 |
8.917 |
8.917 |
Collected by licensed collector |
|
Recycled Paper / Cardboard
Packing (¡¥000 kg) |
9.309 |
0.995 |
10.304 |
Collected by paper recycling company |
|
Recycled Plastic (¡¥000 kg) |
0 |
0.215 |
0.215 |
Collected by licensed collector |
|
Chemical Wastes (¡¥000 kg) |
0.132 |
0.015 |
0.147 |
Collected by licensed collector |
|
General Refuses (¡¥000 m3) |
17.414 |
8.328 |
25.742 |
NENT |
7.3.1
Waste management was the contractor¡¦s
responsibility to ensure that all wastes produced during the construction phase
are handled, stored and disposed of in accordance with good waste management
practices and EPD¡¦s regulations and requirements. The Waste Management Plan was
developed by the Contractor to include the recommended mitigation measures in
the construction phase.
7.3.2
During construction phase, regular site
inspection as part of the EM&A procedures were carried out to determine if
wastes are being managed in accordance with approved procedures and the Waste
Management Plan. Different aspects of waste management including waste
generation, storage, recycling, treatment, transport and disposal had included
in the programme. Waste Flow Table implemented by the
Project has properly recorded the total qualities of wastes generated and
disposal arrangement, they were general in line with the EIA Report.
7.3.3
With the implementation of the recommended
mitigation measures for the handling, transportation and disposal of the
identified waste arising, residual impacts are not observed for construction
phases. It is deemed that the solid
and liquid waste management is effective and under control.
8.1.1
According
to the approved EM&A Manual, the environmental site inspection shall be
formulation by ET Leader. Weekly
environmental site inspections should carry out to confirm the environmental
performance.
8.2.1
Throughout the Construction
Period, weekly joint site inspection has been carried out by supervisor,
Contractors, IEC, and ET to evaluate site environmental performance. No
non-compliance was recorded and minor deficiencies were in general rectified
within the specified deadlines. The environmental performance of the two
Contracts as under the Project was therefore considered satisfactory. The summary of site inspection are shown in Table 8-1.
Table 8-1 Summary
of Site Inspection
|
Date |
Number of Sessions |
Inspection Period |
|
Contract 1 |
334 |
29 August 2018 to 30 April 2025 |
|
Contract 2 |
327 |
21 November 2018 to 30 April 2025 |
9.1.1
Pursuant to
Section 13 of the Project¡¦s EM&A Manual, landfill gas monitoring shall
perform during excavation work within the 250m Consultation Zone of Tseung Kwan O Stage II & III Landfill. For landfill gas monitoring
requirements, pre entry and routine measurement shall be undertaken
in accordance with the Factories and Industrial Undertaking (Confined
Spaces) Regulation.
9.1.2
According to Environmental Mitigation Implementation Schedule
(EMIS) S14.7.6, portable monitoring equipment can be used to conduct landfill
gas monitoring. Moreover, the
frequency and areas to be monitored should be set down prior to commencement of
the works either by the Safety Officer or by an appropriately qualified person.
9.2.1
In event of the trigger levels specified in Table 14.6 of the EIA
report being exceeded, a person, such as the Safety Officer, shall be
nominated, with deputies, to be responsible for dealing with any emergency
which may occur due to LFG. In an emergency situation the nominated
person, or his deputies, shall have the necessary authority and shall ensure
that the confined space is evacuated and the necessary works implemented for
reducing the concentrations of gas.
The
Limit levels and relevant Action Plans for landfill gas detected in utilities
and any on-site areas following construction is
listed in Table 9-1.
Table
9-1 Actions in the Event of Landfill Gas Being Detected in
Excavations
|
Parameter |
Limit Level |
Actions |
|
Methane |
>10% LEL (i.e.
>0.5% by volume) |
Post ¡§No Smoking¡¨
signs Prohibit hot works Ventilate to restore
methane to <10% LEL |
|
>20% LEL (i.e.
>1% by volume) |
Stop excavation
works Evacuate
personnel/prohibit entry Increase ventilation
to restore methane to <10% LEL |
|
|
Carbon dioxide |
>0.5% |
Ventilate to restore
carbon dioxide to <0.5% |
|
>1.5% |
Stop excavation
works Evacuate
personnel/prohibit entry Increase ventilation
to restore carbon dioxide to <0.5% |
|
|
Oxygen |
<19% |
Ventilation to
restore oxygen >19% |
|
<18% |
Stop excavation
works Evacuate
personnel/prohibit entry Increase ventilation
to restore oxygen to >19% |
9.2.2
In the event of the trigger levels specified in Table 9-1 being exceeded, the Safety
Officer shall be responsible for dealing with any emergency which may occur due
to landfill gas.
9.3.1
During
the Construction Period, a total of 968 days of landfill gas monitoring
was conducted by the Safety Officer or an approved and qualified person at the
zone Wan O Road which excavation work of Contract 2 was carried out. The
results of landfill gas measurement are summarized in Table 9-2.
Table 9-2 Summary
of Landfill Gas Measurement Results
|
Landfill
Gas Parameter |
Year |
Detectable at LMR |
Action Level |
Limit Level |
|
|
Min |
Max |
||||
|
Methane |
2019 |
0.1% |
0.1% |
>10% LEL (>0.5% v/v) |
>20% LEL (>1% v/v) |
|
2020 |
0.1% |
0.1% |
|||
|
2021 |
0% |
0% |
|||
|
2022 |
0% |
0% |
|||
|
2023 |
0% |
0% |
|||
|
Oxygen |
2019 |
20.8% |
21.1% |
<19% |
<18% |
|
2020 |
20% |
22% |
|||
|
2021 |
20.6% |
20.8% |
|||
|
2022 |
20.3% |
21.1% |
|||
|
2023 |
20.3% |
20.7% |
|||
|
Carbon Dioxide |
2019 |
0.1% |
0.2% |
>0.5% |
>1.5% |
|
2020 |
0.1% |
0.2% |
|||
|
2021 |
0% |
0% |
|||
|
2022 |
0% |
0% |
|||
|
2023 |
0% |
0% |
|||
9.3.2
According to the measurement results, it is shown
that slightly methane and carbon dioxide concentration was detected at the zone
Wan O Road where the excavation work was carried out during the period. Oxygen
concentration during the excavation work period was over 19.0%
9.3.3
No exceedance was triggered and therefore no
corrective action was required accordingly in the excavation work period. Database
of the landfill gas monitoring results can be referred to the corresponding
monthly EM&A Reports.
10.1.1
Throughout
the Construction Period, a total of 55 environmental complaints were lodged
under the EM&A Programme. ET had performed
investigations by auditing the mitigation measures implemented by the
Contractor. Following the investigations, 16 out of 55 complaints were
considered as project related complaint. The Contractors were advised to
implement and enhance the relevant mitigation measures. Site check was
conducted by ET to check the environmental performance after the situation has
been rectified.
10.1.2
Neither environmental summons nor
prosecutions were received for the Project throughout the Construction Period. The
statistical summary table of environmental complaint is presented in Tables
10-1, 10-2 and 10-3.
A summary of complaint log is shown on Appendix I.
Table 10-1 Statistical
Summary of Environmental Complaints
|
Contract No |
Contract Period |
Environmental
Complaint Statistics |
|
|
Cumulative
Complaint |
Project related
complaint |
||
|
Contract 1 |
3 Dec 2018 ¡V 30 Apr 2025 |
33 |
11 |
|
Contract 2 |
17 Jan 2019 ¡V 30 Apr
2025 |
26 |
9 |
Table 10-2 Statistical
Summary of Environmental Summons
|
Contract No |
Contract Period |
Environmental Summons
Statistics |
|
|
Cumulative Summons |
Summons Nature |
||
|
Contract 1 |
3 Dec 2018 ¡V 30 Apr 2025 |
0 |
NA |
|
Contract 2 |
17 Jan 2019 ¡V 30 Apr
2025 |
0 |
NA |
Table 10-3 Statistical
Summary of Environmental Prosecution
|
Contract No |
Contract Period |
Environmental Prosecutions
Statistics |
|
|
Cumulative
Prosecutions |
Prosecutions |
||
|
Contract 1 |
3 Dec 2018 ¡V 30 Apr 2025 |
0 |
NA |
|
Contract 2 |
17 Jan 2019 ¡V 30 Apr
2025 |
0 |
NA |
11.1.1
The environmental mitigation measures that recommended in the
Implementation Schedule for Environmental Mitigation Measures (ISEMM) in the approved
EM&A Manual covered the issues of dust, noise,
water and waste and they are summarized presented in Appendix H.
11.1.2
The Contractors had
been implementing the required environmental mitigation measures according to the
Environmental Monitoring and Audit Manual subject to
the site condition. Environmental
mitigation measures generally implemented by the Contractors in the
Construction Period are summarized in Table 11-1.
Table 11-1 Environmental
Mitigation Measures in the Construction Period.
|
Issues |
Environmental Mitigation Measures |
|
Construction Noise |
¡P Regularly to
maintain all plants, so only the good condition plants were used on-site ; ¡P If possible,
all mobile plants onsite operation has located far from NSRs; ¡P When
machines and plants (such as trucks) were not in using, it was switched off; ¡P Wherever
possible, plant was prevented oriented
directly the nearby NSRs; ¡P Provided
quiet powered mechanical equipment to use onsite; ¡P Weekly noise
monitoring was conducted
to ensure construction noise meet the criteria. |
|
Air Quality |
¡P Stockpile of
dusty material was covered entirely with impervious sheeting or sprayed with
water so as to maintain the entire surface wet; ¡P The construction plants
regularly maintained to avoid the emissions of black smoke; ¡P The construction plants
switched off when it not in use; ¡P Water spraying on haul road and dry site area
was provided regularly; ¡P Where a vehicle leaving
the works site is carrying a load of dusty materials, the load has covered
entirely with clean impervious sheeting; and ¡P Before any vehicle leaving
the works site, wheel watering has been performed. |
|
Water Quality |
¡P
Debris and refuse generated on-site collected daily; ¡P
Oils and fuels were stored in designated areas; ¡P
The chemical waste storage as sealed area provided; ¡P
Site hoarding with sealed
foot were provided surrounding the boundary of working site to prevent
wastewater or site surface water runoff get into public areas; and ¡P
Portable chemical toilets were provided on-site. A licensed contractor was regularly disposal and maintenance of these facilities. ¡P
Silt
curtain was installed and maintained in accordance with EP condition |
|
Waste and Chemical Management |
¡P Excavated material reused on site as far as possible to minimize
off-site disposal. ¡P Scrap metals or abandoned equipment should be recycled if possible; ¡P Waste arising kept to a minimum and be handled, transported and
disposed of in a suitable manner; ¡P Disposal of C&D wastes to any designated public filling facility
and/or landfill followed a trip ticket system; and ¡P Chemical waste
handled in accordance with the Code of Practice on the Packaging, Handling
and Storage of Chemical Wastes. |
|
General |
The site is
generally kept tidy and clean. Mosquito control is performed to prevent
mosquito breeding on site. |
11.2.1
According
to Environmental Permit EP-459/2013 Condition 3.4, noise mitigation measures
such as low noise surfacing and semi-enclosure noise barrier shall be
implemented at CBL main bridge and Road D9 to mitigate traffic noise impact
arising from the operation of Project. The details of the mitigation measures
are shown in Table 11-2. All the locations and dimensions of the required
mitigation measures are complied with Table 1 and Figure 2 of the EP.
Table 11-2 Noise Mitigation Measures during
Operation of the Project
|
No. |
Required Mitigation Measures |
Actual Mitigation Measures Implemented |
|
N1 |
Approx. 300m long low
noise surfacing |
400m long low noise
surfacing |
|
N2 |
Approx. 960m long low
noise surfacing |
1060m long low noise
surfacing |
|
N3 |
Approx. 220m long 6m
height + 17m width semi-enclosure |
220m long 6.6m height +
17m width semi-enclosure |
|
N4 |
Approx. 245m
long 6m height + 10.5m width semi-enclosure |
245m long 6.3m height + 10.7m width semi-enclosure |
|
N5 |
Approx. 22m
long 6m height +13.2m width semi-enclosure |
22m long
6.3m height + 13.7m width semi-enclosure |
|
N6 |
Approx. 33m long 6m height +
17.4m width semi-enclosure |
33m long 6.3m height + 17.4m
width semi-enclosure |
|
N7 |
Approx.
90m long 6m height + 13.5m width semi-enclosure |
90m long 6.3m height + 13.7m width semi-enclosure |
|
N8 |
Approx.
55m long low noise surfacing |
55m long low noise surfacing |
12.1.1
This is the
Final EM&A Report for Construction Phase for Contracts 1 and 2, summarizing
the monitoring results and inspection findings during the construction period
from 3rd
December 2018 to 30th April 2025.
12.1.2
Throughout the Construction Period, 1-hour TSP and 24-hour TSP
were conducted based on the EM&A requirement. Both 1-hour TSP and 24-hour
TSP monitoring results throughout the Construction Period were below the Action
/Limit Levels.
12.1.3
Throughout the Construction Period, a total of 38 Action Level and
110 Limit Level exceedances were recorded at the designated construction noise
monitoring stations. NOEs were issued to the corresponding parties upon
confirmation of the monitoring result, and subsequent investigations for the
causes of exceedances were conducted by the ET. Based on the investigation
results, 15 out of 38 Action Level exceedances were considered as project
related. Upon
receipt of the complaint, the Contractor had taken
immediate action to implement relevant noise mitigation measures to further
minimize the noise impact. Although
there were 110 Limit Level exceedances recorded throughout the construction
period, they were considered as project unrelated. However, Contractors were reminded to strictly
implement the noise mitigation measures as far as practicable to reduce to
noise impact to the public
12.1.4
Throughout the Construction Period, a total of 22 Action Level and
33 Limit Level exceedances were recorded at the water quality monitoring
stations for the parameters of Dissolved Oxygen, Turbidity, and Suspended
Solids. NOEs were issued to the relevant parties upon confirmation of the
monitoring result, and subsequent investigations for the causes of exceedances
were conducted by the ET. Although the investigation results of the exceedances
are project unrelated, both Contractors are reminded to pay special attention
water quality mitigation measures and should fully implement the measures
recommended in the EM&A Manual.
12.1.5
Throughout the Construction Period, a
total of 968 days of landfill gas monitoring was conducted by the Safety
Officer or an approved and qualified person at the zone Wan O Road which
excavation work of Contract 2 was carried out. No exceedance was triggered and
therefore no corrective action was required accordingly in the excavation period.
12.1.6
Throughout
the Construction Period, a
total of 334 sessions of site inspections were conducted for Contract 1, and
327 sessions for Contract 2 were conducted by the ET to evaluate the
environmental performance of both contracts.
No non-compliance was recorded on both contracts, and minor deficiencies were
generally rectified within the special deadlines. Therefore, the environmental
performance of both contracts under the project was considered satisfactory.
12.1.7
An Independent Environmental Inspector
(IEC) joined monthly site inspection with the Representative Engineer (RE), the
Contractors and ET. A total of 76 audits were performed for Contract 1 and 74
for Contract 2 throughout the Construction Period. No non-compliance issues
were identified; however, minor deficiencies were noted and were generally
rectified within the specified deadlines. This collaborative effort contributed
to maintaining effective environmental oversight and compliance for both
contracts.
12.1.8
Throughout the Construction Period, a total of 55 environmental
complaints were lodged under the EM&A Programme.
ET had carried out investigations by auditing the mitigation measures
implemented by the Contractor. After investigation, 16 out of 55 complaints
were considered as project related. The Contractor was strongly advised to
implement and enhance the relevant mitigation measures. Site check was
conducted by ET to check the environmental performance after the situation has
been rectified.
12.1.9
Throughout the Construction Period, no environmental summons or
prosecutions were received for the project.
12.1.10
To conclude, monitoring results of air quality, construction
noise, and water quality in general indicated satisfactory environmental
performance of the Project. The environmental mitigation measures as
recommended in the ISEMM are also proven effective and adequate.
12.2.1
Precision of the prediction of the EIA on the adverse
air quality, noise, and water quality impacts as generated from the
construction of the Project is acceptable. The monitoring performed during the
Construction Period is effective for generating data with the necessary
statistical power to categorically identify or confirm the presence and absence
of the predicted environmental impacts attributable to the works under the
Project.
12.2.2
The mitigation measures stipulated in ISEMM included
air quality, noise, and water quality are effective and shall be strictly
implemented and observed throughout the construction period in future of other
construction projects to ensure ongoing environmental protection and
compliance.